Good-bye destruction, Hello construction






It looks like we are really finished with the destruction phase of this project. We've even started clearing out the debris, although there is still a pretty good pile of stuff in the back. Our views from the basement windows are still of mounds of dirt and stone, and a few basement stairs.




Speaking of stairs, I guess the team got tired of that ladder, so they built a temporary staircase from the 1st floor to the basement. The treads are a little narrow, but at least you don't have to go down backwards. But before that happened, Ken cut back on the foundation wall so we will have more space in the stairwell it will look a lot more inviting to go down into the basement and not a dungeon.


The framing in the basement is nearly done, and the definitions of the spaces look great. Unfortunately, it doesn't show up well on photos (at least not my photos).

The plumber has begun doing the pipes and valves throughout the house. I'm trying to keep about 1/2 step ahead of him in selecting sinks, faucets, etc. We have decided to re-use a pedestal sink from the 3rd floor in the basement powder room. It's a bit of an '80's throwback, but we'll get a 21st century faucet for it. It just seems wrong to toss some of this perfectly good stuff.



On Sunday, Peter and I went to make some decisions that Lee needs right away. Here's a photo of Peter on the fabulous bluestone landing for our new vestibule entry.
Then Simon-the-builder came over in his hard hat to check out our progress and give us the ok to continue. I'm not sure what he remembers of the house the way it was, but he was pretty interested in the big mess everywhere.

The electrician is supposed to start on Wednesday which means finalizing outlets, light switches, etc. We are also hoping to finalize the built-in configurations. Another busy week - hopefully it'll be a little drier than last week.

Tuesday, April 17, 2007

Rain, rain go AWAY

I stopped in at the house this morning to see what kind of havoc might have occured in the basement from the heavy rains and winds. It was actually surprisingly dry. There were a few shallow puddles, but nothing that Lee didn't expect. Nothing seeped up from the new floor and once we have real windows and the insulation on the walls, it should be really tight. Probably the drain at the bottom of the new vestibule steps also helped.








The lumber was delivered for the framing in basement. Katelyn and Ken had to lug it all inside so it wouldn't get soaked. Tuesday is framing day.






One of the concrete guys came back to score the basement floor.Lee explained: concrete cracks - that's a fact. So we cut lines in the concrete to direct the cracks. For example, the lines in sidewalks are put there, not for kids'games (step on a crack...) or for aesthetic reasons. It is to make the natural cracks happen in straight lines. In our case, chalk mark was drawn in various places, then the scoring was done with a little gas-powered machine. All very neat and very straight.












Before the tile goes on the floor, there will be a thin membrane put down which will buffer any movement of the concrete and keep the tile or grout from cracking.






Apparently Lee has abandoned the Mary Poppins idea and there is a ladder going from the first floor down to the basement. I prefer to go outside and come in through the basement door.



Chris and his team were here over the weekend continuing with the ductwork. I took some shots of more 3rd floor ducts but it was pretty dark thanks to this weather so it's hard to see.





The rest of the week is supposed to be rainy or snowy and cold, so I guess the masons won't be around. Barry Burbank has promised that nice weather will start this weekend and it will be warm and sunny by Monday. We'll see...

Friday, April 13, 2007

The concrete is in


When I got to the house this morning, I found a veritable beehive of activity. Or at least there were alot of trucks and alot of people. Actually I got there in time for coffee break:



Unfortunately, I arrived later than I had hoped to, and the concrete had already been poured into the basement. I'm really sorry I missed it; I guess they hose it in to different areas and then spread it. I got there in time to see them put the hoses away. Then they had to wait for it to set up for a few hours and then they could smooth it out. I got to see that part. There's a machine that does it kind of like a floor waxer going over the floor. And of course there is the old-fashioned way with a guy with a trowel down on his knees.





The new den has become a duct factory. I found Chris the HVAC guy in there insulating ducts. And they've started laying out the ducts on the 3rd floor. When I returned in the afternoon, there were already ducts up in the 3rd floor ceiling. This is another validation of blowing away the existing 3rd floor - more flexibility for designing HVAC on 3rd and 2nd floors.

I was also surprised to find Mike the mason at the house since the weather is so damp and cold. I hadn't even realized, but while we were away, they finished the bluestone terrace around the living room. It looks great. Today they started on the bluestone by the new back door entrance.




Katelyn was busy making mockups of the new compressors so we can see how to place them outside. It turns out we will only need 3, not 4, so even if they are bigger than the old ones they'll still take up less space. And Lee says they are very quiet.
I found the basement stairs lying on top of a pile of junk in the back yard. Out with the old; renovation can be pretty brutal sometimes. And here's a photo of the view of the basement from where the stairs used to be. We're trying to decide between putting in a fireman's pole or an elevator to replace the stairs. Lee suggested we just have a bunch of umbrellas and float down a la Mary Poppings.
And of course the back stairs are off limits now since they were supported by the basement stairs.

Lee is hoping to start framing in the basement on Tuesday. And he and I are going to take a field trip one day next week to check out a couple of vanities for the bathrooms.

I think the drainage system in the basement went in just in time since there are predictions for a northeaster and about 5 inches of rain over the weekend. I'm curious to see if the new concrete floor remains dry.

A day at the beach





I finally got back to the house yesterday afternoon. The basement is amazing: with no stairs and no extaneous walls, it looks huge. And now the floor is nicely covered with a layer of sand - it really does look like a beach. Lee explained all the layers that went down before the sand came in, including stone, a moisture barrier, and a lovely shiny blue material and then the sand. I guess the pea stone and the sand was shot in through one of the windows, filling up a space over 8 feet high and then had to be raked all over the floor. I'm really sorry I missed it, but Lee has photos that I will get one of these days. In the meantime here's the finished product:






It seems that the drainage system that they devised for under the floor is also wrking. In spite of torrential and persistant rain yesterday, the sand was dry. Yay.
The HVAC ductwork for the indoor outdoor room has been buried in the floor so we can only see where the ducts emerge to be connected. The same is true for the plumbing pipes. It is all so neat.






Outside, by the vestibule door, I noticed the heating cables were laid. I don't think they were there before I left, but it's been so long I don't really remember. Anyway, here they are.




This morning the concrete is supposed to be poured for the basement floor. So I'm going to the house now to see how that goes.




Wednesday, April 11, 2007

Update

I spoke to Lee this morning to get an update. I guess they are busy preparing the basement floor for the concrete which is now scheduled to come on Friday morning since Thursday is supposed to be pretty wet and slushy. Maybe nice weather in January isn't really worth it if the price we pay is winter in April. At least alot of outside work got done during the winter so this shouldn't throw us off schedule, but I'm anxious to start planning the landscaping.

The stairs from the house to the basement have been removed. Apparently Lee discovered this when he went to go down to the basement this morning. Hopefully we'll be able to plan the new staircase to be more open and inviting and still have some storage space on the walls.

Assuming all goes well with the concrete, the team will be able to start framing the walls in the basement next week. Then comes wiring, plumbing and then we're just about done! Right?

I can't wait to get back to see the changes of the last 10 days. Photos will start again on the next blog if Delta cooperates and my bag with my camera comes home with me.

Friday, April 06, 2007

Oops

I guess Spring took a break and there has been some snow and cold - I hope the wisteria is ok, and all the bulbs that started coming up. Mother nature can be challenging.

We've been away for the week and will e away for the next week, so no photos. But I do get updates from Lee.

It sounds like a lot of progress has been made in the basement. The drainage system is in; the plumbing pipes are all in the floor and all the lally columns have been secured or removed and the house is still standing.

Next week the concrete guys are scheduled to come to pour the floor in the basement. Then the framing can be done. Very exciting.